74-344 考試一旦沒通過,報名費就得再繳一次,重考成本不容小覷。與其事後補救,不如先用 Fast2test 的 Microsoft Managing Programs and Projects with Project Server 2013 練習題充分演練,把 97 道題目練熟練透再上場。
Microsoft 74-344 考試概覽:
| 認證廠商: | Microsoft |
|---|---|
| 考試名稱: | 使用 Microsoft Project Server 2013 管理方案與專案 |
| 考試代碼: | 74-344 |
| 支援語言: | English |
| 及格分數: | 700/1000 |
| 考試時間: | 120 分鐘 |
| 相關認證: | Microsoft Project 與組合管理 Microsoft Project Server 2013 |
| 考試形式: | 選擇題, 個案研究題, 情境導向題 |
| 推薦課程: | Microsoft Learn 專案管理相關資源 |
| 範例考題: | Microsoft 74-344 範例考題 |
| 考試方式: | 電腦化監控考試,可透過授權考場或線上監考方式應考(以往由 Pearson VUE 提供服務) |
| 必備條件: | 無強制報考資格;建議具備 Microsoft Project Server 2013 操作經驗與企業專案管理相關概念。 |
Microsoft 74-344 考試大綱主題:
| 章節 | 目標 |
|---|---|
| 報表與商業智慧 | - 資料分析與績效監控 - 儀表板與關鍵績效指標(KPI)追蹤 - 透過 Project Server 製作報表 |
| 專案與方案管理概念 | - Project Server 2013 的專案生命週期與治理機制 - 企業專案與方案管理基礎知識 |
| 專案執行與協作 | - 專案排程與進度追蹤 - 工時表與工作更新作業 - 團隊協作與 SharePoint 整合應用 |
| Project Server 2013 設定與管理 | - 安全性與權限模型 - Project Web App(PWA)設定 - 企業專案類型(EPT)與工作流程 |
| 組合與資源管理 | - 需求管理與資源配置 - 組合分析與優先順序排定 - 資源庫與產能規劃 |
Microsoft Managing Programs and Projects with Project Server 2013 考生常見問題解答
Microsoft Managing Programs and Projects with Project Server 2013(考試代碼 74-344)是 Microsoft 官方規劃的認證考試,通過後可取得「Microsoft 認證專業人員(舊版 Project Server 2013 考試系列)」認證,認證等級為 專業級。此認證亦與 Microsoft Project Server 2013、Microsoft Project 與組合管理 等認證相互關聯,可依職涯規劃進一步進修。若您正準備這門考試,Fast2test 收錄的 97 道練習題能協助您有系統地複習每個知識要點。
無強制報考資格;建議具備 Microsoft Project Server 2013 操作經驗與企業專案管理相關概念。由於官方可能隨時調整報考規定,建議您報名前再至 Microsoft 官方網站確認最新資訊,以免影響報名資格。
74-344 考試可透過以下官方管道報名:
本考試的考試方式為:電腦化監控考試,可透過授權考場或線上監考方式應考(以往由 Pearson VUE 提供服務)。
完成報名後,建議儘早開始使用 Fast2test 的練習題規劃複習進度,讓備考節奏更從容。
有的,Microsoft 官方針對 74-344 提供下列推薦培訓資源:
官方課程適合建立觀念基礎,課後再搭配 Fast2test 的 97 道 74-344 練習題反覆演練,複習效果會更加完整。
可以。Fast2test 提供 Microsoft Managing Programs and Projects with Project Server 2013 的免費範例試題,您可先下載體驗題目品質與解析方式,滿意後再決定購買。購買後享有 365 天免費更新,期間題庫有任何修訂都可免費取得最新版本;即使產品過期,後續續購更新仍可享 50% 折扣優惠。
交付方面,Fast2test 採即時交付:付款完成後一分鐘內,下載資訊即寄送至您的電子郵件信箱,若 2 小時內仍未收到可聯絡客服協助,且產品不限制安裝的電腦數量。考試方面,我們提供退款保證:購買後 60 天內參加對應考試而未通過者,可於考後 2 天內提交報名證明(准考證)影本與官方成績單(Score Report)PDF 申請全額退款,我們會在 7 天內處理完成;考生姓名須與付款人姓名一致,購買後 3 天內即應考、已下載但未實際應考,以及免費資料與過期訂單均不適用。若您不想退款,也可選擇免費更換為兩個等值考試資料,並保留原購產品的更新服務。
74-344 考試共劃分為 5 個主要領域,包括 報表與商業智慧、組合與資源管理、Project Server 2013 設定與管理 等。各領域的完整細項與說明請參考上方的考試大綱,建議您依各領域的佔比高低安排複習比重,把時間花在最關鍵的主題上。
最新的 Microsoft Project 74-344 免費考試真題:
問題 #1
Your organization is using Project Online to facilitate the selection of optimal portfolios.
The Project Management Office (PMO) expects to analyze the portfolio of projects in a short period of time by using the efficient frontier and the strategic value provided by the tool.
You need to ensure the tool provides the expected outcome.
Which three actions should you perform? (Each correct answer presents part of the solution. Choose three.)
A. Create a custom field to be used as alias when force-in or force-out options are selected.
B. Create a custom cost field to be used as a cost constraint.
C. Define the list of projects that include cost estimates.
D. Define and rank specific business drivers or other factors relevant to the project approval process.
E. Create a custom workflow that allows the capture of projects with business-relevant information.
F. Populate and configure the resource pool, including maximum units, resource calendars, and a primary role field.
問題 #2
You are a project manager for an organization that uses Project Server 2013.
You create a complex schedule that has many segments which are divided by your organization's departments and external vendors. The duration of the schedule is 18 months. After six months, you learn that a different department may do some of the upcoming work.
While upper management decides which department they need to perform the work, you realize that your schedule has numerous assignments that now may be done by another department. You do not want to delete the assignments because you have many interdependencies among these tasks and the rest of your schedule. However, you cannot have resources working on these tasks at this time.
You need to keep your tasks in your schedule so upper management can view them, and you need to ensure that the team members do not work on or update those tasks.
What should you do?
A. Delete the tasks
B. Inactivate the tasks
C. Set the tasks to manually scheduled
D. Lock the tasks
問題 #3
You are an administrator in an organization that uses Project Server 2013. Single entry mode is disabled.
Resources use the Tasks page in Project Web App (PWA) to report task progress. You need to ensure that resources have the ability to report work actuals per day.
What should you do?
A. Set the tracking method to actual work done and work remaining.
B. Set the tracking method to hours of work done per period.
C. Enable the option to allow users to define custom periods for task updates.
D. Set the tracking method to percent of work complete.
問題 #4
You are a project manager in an organization that uses Project Server 2013. All project
managers have permission to edit all projects.
You edit a project in Project Web App (PWA), make changes, publish the project, and close
your browser.
A project manager calls you to report they are unable to open your project for edit in PWA. You need to resolve this issue. What should you do?
A. Open the Project Center in PWA and use the Check in My Projects button.
B. Open the Project Center in PWA and use the Project Permissions button.
C. Advise the project manager to open the project in Project Professional 2013.
D. Open Project Professional 2013 and use the Clean Up Cache button.
問題 #5
Your company uses Project Server 2013 to evaluate and select projects based on a primary cost constraint, as well as a secondary constraint of internal rate of return (IRR).
Management authorizes a budget and establishes a minimal IRR of 5% to execute any project the following year. Your company has never analyzed constraints other than cost.
As the portfolio analysis expert, you need to recommend a reasonable approach to perform the analysis.
What should you recommend?
A. Create a new analysis through Portfolio Analysis and select the primary cost constraint. Then select an alias to force-out when defining properties and name it IRR.
B. Create a new analysis through portfolio analysis and select the primary and secondary constraints when defining properties.
C. Create the analysis and, during the cost analysis, introduce the secondary constraint to automatically force out the non-compiling projects.
D. Create the analysis and, during the cost analysis, introduce the secondary constraint to manually force out the non-compiling projects.
問題與答案:
| 問題 #1 答案: C,D,F | 問題 #2 答案: D | 問題 #3 答案: B | 問題 #4 答案: A | 問題 #5 答案: D |
1116條客戶評論客戶反饋 (*一些類似或舊的評論已被隱藏。)
我無法形容此刻我的心情,要是沒有 Fast2test 提供的考古題,我不能確定我能通過 74-344 考試,你們提供的題庫非常完美,很高興當初購買了這考題。
這考古題很好,我通過了第一次嘗試參加的74-344認證考試,它涵蓋了我需要知道的考試題庫,幫助我輕松通過!
你們的74-344考試題庫很不錯,所有真實考試中的問題都涉及到了。
這考古題很好,我通過了第一次嘗試參加的74-344認證考試,它涵蓋了我需要知道的考試題庫,幫助我輕松通過!
由于有你們Fast2test網站的74-344考試培訓資料,我通過了考試并獲得了證書。
我已经通过了今天的 74-344 考試,谢谢你們提供的帮助,我很慶幸從 Fast2test 網站购买了這個学习指南,因为這個指南是非常简单易懂的,讓我輕松的通過了考試。
前段時間買了這門74-344題庫,結果正好遇到Microsoft變題,幸好你們及時發給我更新題庫,今天考試了,過程很順利。感謝Fast2test!
今天通過了我的74-344考試,我使用了你們的題庫在我的考試中,這題庫非常好,對我的幫助很大。
我通過了我的74-344考試,不得不承認,這是我用過最好的題庫。因此,我能很容易的通過我的考試多虧了Fast2test網站的最新題庫。
通過了74-344考試,你們的題庫和真實中的Microsoft考試所遇到的問題幾乎是一樣的。
我已經用了你们的產品,并在我的考試中取得很不錯的成績,如果沒有 Fast2test,我的 74-344 考試是不可能通过的。
非常有效的題庫,我的 74-344 考试通過了!這都是因为有 Fast2test 提供的考古題,使我的 74-344 考試變的非常简单。非常感謝你們!
這個考試題庫是非常有用的,我的74-344考試順利的通過了。
上周通過Microsoft 74-344認證,成績91%!出題率超高,感謝有這個好的認證考題。
這個考試題庫是非常有用的,我的74-344考試順利的通過了。
通過了74-344考試,你們的題庫和真實中的Microsoft考試所遇到的問題幾乎是一樣的。
謝謝你們網站提供了這么優秀的考古題資料,我通過了我的74-344考試,在測試中,你們的題庫非常有用!
立即下載 74-344
付款後,我們的系統會在付款後壹分鐘內將您購買的產品發送到郵箱。如2小時內未收到,請與我們聯系。
365天免費更新
購買後365天內可免費升級。365天之後,您將獲得50%的更新折扣。
退款保證
如果您在購買後60天內沒有通過相應的考試,可以全額退款。並且免費獲得任何其他產品。
安全與隱私
我們尊重客戶的隱私。 我們使用McAfee的安全服務為您的個人信息提供最高安全性,讓您高枕無憂。