You are a portfolio manager in an organization that uses Project Server 2013.
You plan to review the milestones status of a project named Proj1.
You need to create a graphical view of all milestones of Proj1 that allows you to see the Start and Finish dates of each milestone. You need to accomplish this goal in the least amount of time.
What should you do?
You plan to review the milestones status of a project named Proj1.
You need to create a graphical view of all milestones of Proj1 that allows you to see the Start and Finish dates of each milestone. You need to accomplish this goal in the least amount of time.
What should you do?
正確答案: D
You are the administrator of a Project Server 2013 environment.
You set up an enterprise custom resource field to define skill sets for resources. When trying to replace your generic resources, the matching function does not work.
You need to reconfigure Project Server 2013 to enable the skills match function.
What should you do?
You set up an enterprise custom resource field to define skill sets for resources. When trying to replace your generic resources, the matching function does not work.
You need to reconfigure Project Server 2013 to enable the skills match function.
What should you do?
正確答案: B
You are a project manager for an organization that uses Project Server 2013.
You manage a schedule with a Project Site, which includes a section for documents that team members and other stakeholders need. You have a very large number of documents that you want to put into the Project Site.
You need to upload these documents by using the most efficient method.
What should you do?
You manage a schedule with a Project Site, which includes a section for documents that team members and other stakeholders need. You have a very large number of documents that you want to put into the Project Site.
You need to upload these documents by using the most efficient method.
What should you do?
正確答案: C
You are a project manager in an organization that uses Project Online. Project managers
have access to Project Professional 2013 for schedule management.
You create a project schedule with resource assignments on Monday. No resources are overallocated. However, on Tuesday, you open the same project schedule and discover on several of your tasks that resources show as overallocated.
Your project has a lower priority than other projects in the organization.
You need to solve the overallocation by adjusting the Scheduled Start for the resources on your tasks to when the resources are available.
What should you do?
have access to Project Professional 2013 for schedule management.
You create a project schedule with resource assignments on Monday. No resources are overallocated. However, on Tuesday, you open the same project schedule and discover on several of your tasks that resources show as overallocated.
Your project has a lower priority than other projects in the organization.
You need to solve the overallocation by adjusting the Scheduled Start for the resources on your tasks to when the resources are available.
What should you do?
正確答案: C
You are a project administrator and are implementing Project Server 2013 for a large organization.
You are asked to ensure that resource assignments, work load, and completion of work can be reported and rolled up by organizational structure.
You need employ the correct functionality in order to configure Project Server 2013.
What should you do?
You are asked to ensure that resource assignments, work load, and completion of work can be reported and rolled up by organizational structure.
You need employ the correct functionality in order to configure Project Server 2013.
What should you do?
正確答案: A
You are a project manager for an organization that uses Project Server 2013.
You create a complex schedule that has many segments which are divided by your organization's departments and external vendors. The duration of the schedule is 18 months. After six months, you learn that a different department may do some of the upcoming work.
While upper management decides which department they need to perform the work, you realize that your schedule has numerous assignments that now may be done by another department. You do not want to delete the assignments because you have many interdependencies among these tasks and the rest of your schedule. However, you cannot have resources working on these tasks at this time.
You need to keep your tasks in your schedule so upper management can view them, and you need to ensure that the team members do not work on or update those tasks.
What should you do?
You create a complex schedule that has many segments which are divided by your organization's departments and external vendors. The duration of the schedule is 18 months. After six months, you learn that a different department may do some of the upcoming work.
While upper management decides which department they need to perform the work, you realize that your schedule has numerous assignments that now may be done by another department. You do not want to delete the assignments because you have many interdependencies among these tasks and the rest of your schedule. However, you cannot have resources working on these tasks at this time.
You need to keep your tasks in your schedule so upper management can view them, and you need to ensure that the team members do not work on or update those tasks.
What should you do?
正確答案: D
Your organization is using Project Online to facilitate the selection of optimal portfolios.
The Project Management Office (PMO) expects to analyze the portfolio of projects in a short period of time by using the efficient frontier and the strategic value provided by the tool.
You need to ensure the tool provides the expected outcome.
Which three actions should you perform? (Each correct answer presents part of the solution. Choose three.)
The Project Management Office (PMO) expects to analyze the portfolio of projects in a short period of time by using the efficient frontier and the strategic value provided by the tool.
You need to ensure the tool provides the expected outcome.
Which three actions should you perform? (Each correct answer presents part of the solution. Choose three.)
正確答案: C,D,F
說明:(僅 Fast2test 成員可見)
You are a project manager in an organization that uses Project Server 2013.
The internal audit department plans to review one of your projects. The audit will include a regular revision of all project documents, risks, and issues.
You need to assign read-only access to an internal auditor so the auditor can access the project's Project Site only.
What should you do?
The internal audit department plans to review one of your projects. The audit will include a regular revision of all project documents, risks, and issues.
You need to assign read-only access to an internal auditor so the auditor can access the project's Project Site only.
What should you do?
正確答案: C
You are a project manager who uses Project Server 2013 and Project Professional 2013. You build a project with common tasks for which many resources on your team can be used.
Because your resources have responsibilities outside of the project, you would like to have them assign themselves to tasks they are able to complete.
You need to configure your resources to enable this method of assigning tasks.
What should you do?
Because your resources have responsibilities outside of the project, you would like to have them assign themselves to tasks they are able to complete.
You need to configure your resources to enable this method of assigning tasks.
What should you do?
正確答案: A
You are a project manager in an organization that uses Project Server 2013. You have access to Project Web App (PWA) but no access to Project Professional 2013 for making changes to your schedule.
In your organization, projects begin work after the project sponsor provides funding for the first phase of the project.
You need to take a snapshot of your schedule and make that information available to the Project Management Office (PMO), who will view it in PWA.
What should you do?
In your organization, projects begin work after the project sponsor provides funding for the first phase of the project.
You need to take a snapshot of your schedule and make that information available to the Project Management Office (PMO), who will view it in PWA.
What should you do?
正確答案: B