最新的Scrum Professional Scrum Master I - PSM-I免費考試真題

An organization has decided to adopt Scrum, but management wants to change the terminology to fit with terminology already used. What will likely happen if this is done? (Choose the best answer.)

正確答案: A
說明:(僅 Fast2test 成員可見)
What is included in the Sprint Backlog?

正確答案: E
說明:(僅 Fast2test 成員可見)
Which Scrum Value is affected by a lack of trust in the Scrum Team?

正確答案: C
說明:(僅 Fast2test 成員可見)
When does a Developer become accountable for an item in the Sprint Backlog? (Choose the best answer.)

正確答案: B
說明:(僅 Fast2test 成員可見)
A new Developer is having continuing conflicts with existing members or the scrum Team, which is impacting the delivery of the Increment It necessary, who is responsible for removing the Developer from the Scrum Team?
(Choose the best answer)

正確答案: C
說明:(僅 Fast2test 成員可見)
When many Scrum Teams are working on the same product, should all of their increments be integrated every Sprint?

正確答案: A
說明:(僅 Fast2test 成員可見)
What is a Development Team responsible for? (Choose two.)

正確答案: B,D
說明:(僅 Fast2test 成員可見)
Which two things are appropriate for a Scrum Master to do, if the Scrum Team does not have the tools and environment to completely finish each selected Product Backlog item? (Choose the best two answers)

正確答案: B,E
說明:(僅 Fast2test 成員可見)
Cross-functional teams are optimized to work on one technical layer of a system only (e.g. GUI, database, middle tier, interfaces).

正確答案: A
說明:(僅 Fast2test 成員可見)
What happens when a Sprint is cancelled? Select three.

正確答案: A,B,D