While preparing the project plan during initiation, the project manager proposes that stage 2 should end at the Council's financial year-end. This would allow the decision on funding for stage 3 to coincide with the Council's annual budget process.
Is this an appropriate application of the 'manage by stages' principle, and why?
Is this an appropriate application of the 'manage by stages' principle, and why?
正確答案: B
說明:(僅 Fast2test 成員可見)
ORGANIZATION
Use the 'Additional Information' in the Scenario Booklet to answer this question.
Here are three roles relating to the LouisShopping Project.
Which individual (A-E) would be MOST appropriate for each role according to the 'organization' practice?
Choose only ONE individual for each role. Each individual can be used once, more than once, or not at all.
Use the 'Additional Information' in the Scenario Booklet to answer this question.
Here are three roles relating to the LouisShopping Project.
Which individual (A-E) would be MOST appropriate for each role according to the 'organization' practice?
Choose only ONE individual for each role. Each individual can be used once, more than once, or not at all.
正確答案: B,D,E
說明:(僅 Fast2test 成員可見)
At the end of the initiation stage, the Regeneration Manager submits the project plan and business case for review. The Portfolio Director releases funding for both stages 2 and 3 and instructs the project manager to provide only a progress report at the end of stage 2, without a project board decision before stage 3 begins.
Is this an appropriate application of the 'manage by stages' principle, and why?
Is this an appropriate application of the 'manage by stages' principle, and why?
正確答案: B
說明:(僅 Fast2test 成員可見)
A new law requires everyone working on public-infrastructure projects to hold an appropriate security clearance. The project manager records the legislation as an external event in the issue register so that its effects can be assessed.
Is this an appropriate application of the issues practice, and why?
Is this an appropriate application of the issues practice, and why?
正確答案: C
說明:(僅 Fast2test 成員可見)
During a periodic evaluation of the security-system work package, the team manager reviews the work package description, team plan, and the related issue, risk, quality, product, and lessons information. Missing electrical cabling means that installation is now forecast to finish one week late, exceeding the work-package time tolerance.
The team manager raises the issue with the project manager and reports the current status in the checkpoint report. Is this an appropriate application of the 'evaluate a work package' activity, and why?
The team manager raises the issue with the project manager and reports the current status in the checkpoint report. Is this an appropriate application of the 'evaluate a work package' activity, and why?
正確答案: B
說明:(僅 Fast2test 成員可見)
At the stage 2 boundary, the project manager recommends adding the replacement subcontractor's account manager to the project board to represent supplier interests during stage 3.
Which practice is being applied in 'managing a stage boundary'?
Which practice is being applied in 'managing a stage boundary'?
正確答案: B