最新的PMI Scheduling Professional - PMI-SP免費考試真題
What is the term assigned to graphic in the figure given below?


正確答案: C
說明:(僅 Fast2test 成員可見)
CORRECT TEXT
Fill in the blank with an appropriate phrase. The ________is defined in terms of either the product or the type of customer or industry sector.
Fill in the blank with an appropriate phrase. The ________is defined in terms of either the product or the type of customer or industry sector.
正確答案:
area
You are the project manager of the AHQ project. This project is scheduled to last for six months and will require $345,000 to complete. If the project completes earlier than scheduled, your organization will receive a bonus of $5,000 per day of early completion. Management has asked you to develop an aggressive schedule to realize as much of the bonus as possible, but management does not want you to increase the costs of the project beyond $1,000 per day of the bonus realization. Which of the following approaches will likely add costs to the project?
正確答案: C
說明:(僅 Fast2test 成員可見)
You work as a Project Manager for Tech Perfect Inc. Several projects are running under your supervision. Martha, the team leader of a project, provides you performance indexes of her project. The cost variance (CV) of her project is -20. What does this figure depict?
正確答案: C
說明:(僅 Fast2test 成員可見)
You are the project manager of the GUH project. You are using the critical chain scheduling method as your approach to project scheduling. What two items can you compare in the critical chain method to determine if corrective action is appropriate?
正確答案: A
說明:(僅 Fast2test 成員可見)
Your project team is executing the project plan and things are going well. Your team has reached its first milestone and is now in the second phase of the project. The project stakeholders have requested that you find a method to reduce the duration of the project. They will reward you and your project team with a 25 percent bonus of the project costs if you can finish the project thirty days earlier than what was already planned. The stakeholders, however, will not approve any additional labor costs as part of the agreement. Which approach could you use to shorten the duration of the project?
正確答案: B
說明:(僅 Fast2test 成員可見)
Harry works as a project manager for BlueWell Inc. He is determining the budget of the project. According to the PMBOK, there are seven inputs to this process. Which one of the following is NOT an input to the determine budget process?
正確答案: D
說明:(僅 Fast2test 成員可見)
John is a scheduler in ABC Company. He has to plan an activity for the schedule models. Which of the following activities will he use to make the schedule models? . Each correct answer represents a complete solution. Choose all that apply.
正確答案: A,C,D
說明:(僅 Fast2test 成員可見)
You are the project manager of the NHG. The following figure represents your project network diagram.

Management has asked that you add some features to the project scope. Through the change control system these changes are approved and they'll affect Activity I.
The duration of Activity I, which is on the critical path, will decrease by three days. What affect does this have on the critical path?

Management has asked that you add some features to the project scope. Through the change control system these changes are approved and they'll affect Activity I.
The duration of Activity I, which is on the critical path, will decrease by three days. What affect does this have on the critical path?
正確答案: C
說明:(僅 Fast2test 成員可見)
You are the project manager of the MQQ project. Unfortunately, this project is not performing well and you must do something to address the problems in your project. Based on your planning for monitoring and controlling project performance, you know that there are three outputs of performance reporting. Which one of the following is the only output that is most appropriate for this poorly performing project?
正確答案: C
說明:(僅 Fast2test 成員可見)
Holly is the project manager for her organization. In her project, she has worked with the project team to define when the project team will be utilized in the project, the duration of the project activities, and the sequence in which the project work must be completed. During several phases of her project, the project team will need to work more than fifty hours per week. The project team members have agreed this is necessary and they're willing to do the work to complete the project. Management, however, has not approved Holly's schedule based on the overtime the scheduling will require. They have set a limit on the project schedule of 45 hours per week. What is this limit technically called? Each correct answer represents a complete solution. Choose all that apply.
正確答案: A,D
說明:(僅 Fast2test 成員可見)