最新的PMI Risk Management Professional - PMI-RMP免費考試真題
The risk manager for a large-scale software-development project with a tight deadline and multiple stakeholders highlights concerns about potential delays, communication gaps, and vendor reliability. During the early stages of the project, the project sponsor asks the risk manager to identify and address any potential risks that could disrupt project delivery.
What should the risk manager do?
What should the risk manager do?
正確答案: A
說明:(僅 Fast2test 成員可見)
A project team identifies that there is a probability of missing a key milestone in a project. The team wants to move forward with the risk response planning.
What should the risk manager complete first?
What should the risk manager complete first?
正確答案: D
說明:(僅 Fast2test 成員可見)
The project's customer has stated the project must be completed by a date indicated as the P90 date established on the Monte Carlo analysis. What should the project manager do to ensure the P90 date is met?
正確答案: B
說明:(僅 Fast2test 成員可見)
The risk manager notices that in their workshops, most of the risks identified are threats. What should the risk manager do to increase the number of opportunities identified?
正確答案: A
說明:(僅 Fast2test 成員可見)
A risk manager has been assigned to a new project and learns that stakeholders and project team members are spread across multiple time zones. Furthermore, many project team members have not worked together in the past. These items are identified as potential risks and added to the risk register.
How should the risk manager improve collaboration during risk planning?
How should the risk manager improve collaboration during risk planning?
正確答案: B
說明:(僅 Fast2test 成員可見)
During the risk management planning, key stakeholders recommend adding more factors other than probability and the impact to refine the score of prioritized threats in subsequent iterations of the qualitative risk analysis. The stakeholders ask the risk manager to prepare a list to discuss this further.
Which three valid factors should the risk manager prepare on the list for discussion? (Choose 3)
Which three valid factors should the risk manager prepare on the list for discussion? (Choose 3)
正確答案: A,D,E
說明:(僅 Fast2test 成員可見)
A risk manager has a well-structured risk management process in place for a complex project with a tight schedule. Despite implementing preventive actions, one of the risks identified in the early stages of the project has still occurred and is now an issue.
What should the risk manager do next?
What should the risk manager do next?
正確答案: B
說明:(僅 Fast2test 成員可見)
A complex project that had hundreds of risks is almost done. The project manager is closing the risks as part of the closing process. One team member mentions that there are important documents to be updated.
Which document will need to be updated?
Which document will need to be updated?
正確答案: B
說明:(僅 Fast2test 成員可見)
A risk manager is collaborating with project stakeholders and the project team to identify risks in a construction project. The risk manager intends to use an approach that engages stakeholders based on information, such as scope baseline and project estimates, while also determining risk impacts based on this approach.
Which risk identification approach should the risk manager use to achieve this goal?
Which risk identification approach should the risk manager use to achieve this goal?
正確答案: A
說明:(僅 Fast2test 成員可見)
A company manages confidential customer information, and a data breach exposing sensitive information was discovered. What should the risk manager do?
正確答案: C
說明:(僅 Fast2test 成員可見)
Some project risks are applicable for the project ' s lifecycle while others risks are only applicable to specific project activities. When should project risks be closed?
正確答案: C
說明:(僅 Fast2test 成員可見)
A project manager for a large product development project assigned a risk manager to perform the risk management. The project sponsor questions why this project requires a risk manager as it is similar to a previous project with a developed risk strategy.
How should the risk manager explain the need for a risk strategy specific to this project?
How should the risk manager explain the need for a risk strategy specific to this project?
正確答案: A
說明:(僅 Fast2test 成員可見)
The stakeholders of a building construction project are not comfortable with the project manager ' s handling of the project as they believe there is a financial risk. The project manager asks the risk manager to assist in demonstrating to the stakeholders that the project risks are under a tolerable threshold.
What should the risk manager do first to demonstrate this to the stakeholders?
What should the risk manager do first to demonstrate this to the stakeholders?
正確答案: B
說明:(僅 Fast2test 成員可見)
A financial institution is beginning a major digital-transformation project to enhance online-banking services.
The risk manager observes that team members from various departments are hesitant to participate actively in risk identification, potentially causing threats and opportunities to be overlooked.
What should the risk manager do?
The risk manager observes that team members from various departments are hesitant to participate actively in risk identification, potentially causing threats and opportunities to be overlooked.
What should the risk manager do?
正確答案: A
說明:(僅 Fast2test 成員可見)