During the fourth sprint retrospective for an IT project, the team members develop a series of actions to improve problem solving in the next sprint. However, many team members are concerned that these actions will not be implemented, since there was no follow-up from the last retrospective meeting.
What should the Scrum Master do to improve team commitment to the recommendations from the retrospective meeting?
What should the Scrum Master do to improve team commitment to the recommendations from the retrospective meeting?
正確答案: A
說明:(僅 Fast2test 成員可見)
If an individual is working on a project team in a phase delivering an increment, according to the definition of done (DoD), who was that defined by?
正確答案: C
說明:(僅 Fast2test 成員可見)
A project team has been working on a new application. The application is technically challenging, because the team is using new technology unknown to the development team and business requirements are unclear. The product owner has been working closely with the stakeholders to ensure alignment with requirements and other issues. The agile lead is working with the team and product owner on the product backlog.
What is the role of the team?
What is the role of the team?
正確答案: C
說明:(僅 Fast2test 成員可見)
When prioritizing features to be delivered in an iteration, on what features should an agile team defer work?
正確答案: C
說明:(僅 Fast2test 成員可見)

An e-commerce company acquired a tool to customize subject line generation for marketing campaigns. In sprint planning, the team discussed integrating this tool with the customer relationship management system.
Which mitigation strategy is most appropriate to ensure the final product meets the business objectives?
(Refer to the Risk Register Exhibit)
正確答案: C
說明:(僅 Fast2test 成員可見)
An agile team is struggling with an issue. A team member mentions that another team had a similar issue that was resolved, but lessons learned documents are unavailable.
What should the agile practitioner do?
What should the agile practitioner do?
正確答案: B
說明:(僅 Fast2test 成員可見)
A team is building a product in three-week iterations. During the last retrospective, it was identified that there was a 20% increase from previous iterations in the number of reported defects and change requests.
Since this is causing the product ' s value to decrease, what should the team do?
Since this is causing the product ' s value to decrease, what should the team do?
正確答案: C
說明:(僅 Fast2test 成員可見)
As user stories are developed, what should be done to record and update acceptance criteria?
正確答案: B
說明:(僅 Fast2test 成員可見)
The transition of a monthly news publication from paper to digital is planned to start in the next few weeks.
There is a debate between the product owner and the development team about the initial features to be made available and the first five stages of implementation.
What should the scrum master do to address this situation?
There is a debate between the product owner and the development team about the initial features to be made available and the first five stages of implementation.
What should the scrum master do to address this situation?
正確答案: A