You want to perform an SAP S/4HANA conversion using SUM with inplace DMO.
Which steps run before the beginniing of the technical downtime, irrespective of your SUM configuration? Note: There are 3 coorrect answers to this question.
Which steps run before the beginniing of the technical downtime, irrespective of your SUM configuration? Note: There are 3 coorrect answers to this question.
正確答案: B,C,E
You are performing an SAP S/4HANA conversion with DMO. You entered a specific nummber of R3load processes during the Extraction Roaadmap step.
Where can you change this during the migration via the Utilities option of the SUM UI?? Note: There are 2 correct answers to this questiion.
Where can you change this during the migration via the Utilities option of the SUM UI?? Note: There are 2 correct answers to this questiion.
正確答案: B,C
What do you need to know about the SAP S/4HANA Conversion Guide? Note: There are 2 correct answers to this question.
正確答案: A,B
Which preparational steps must be performed for an SAP S/4HANA conversion? Note: There are 2 correct answers to this question.
正確答案: A,B
What are the benefits of using the benchmarking option of the DMO for SUM? Note: There are 2 correct answers to this question.
正確答案: B,D