Your costumer Project/planning Board to create/update Gant charts. Which the following are characteristics of the Project Planning Board.
Note : there are 3 correct answers for this question.

正確答案: A,B,E
An external component is assigned to a network activity. The delivery date for the purchase requisition depends on the dates of the network activity.
What controls whether the delivery date is defined by the earliest or latest scheduled dates?

正確答案: C
The various work packages in the project are described as individual______________. Choose the correct answer.

正確答案: A
Which objects can be used to specify settlement rules? Note: There are 2 correct answers to this question?

正確答案: A,D
Float time is calculated during scheduling.
Which of the following statements about float time are correct?
Note: There are 3 correct answers to this question

正確答案: A,B,E
The__________________that you specify when you create a project definition is unique for the entire project. Choose the correct answer.

正確答案: C
You have assigned a budget to WBS elements within your project. What function can be used to check assigned values against the current budget

正確答案: D
What are the prerequisites for delivering materials from the project? Note: There are 2 correct answers to this question

正確答案: C,D
You have activated the workflow for confirmation variances in SAP Project System. Who is the receiver of this workflow item?