The BPM Program Manager revises the project plan after Playback 0. The team has completed further analysis and definition of user stories with point estimates that were validated by both BPM Solution Architect and the user story owners. What is an appropriate level of confidence in the accuracy of this revised estimate at this stage in the project life cycle?

正確答案: C
The BPM Program Manager, Process Owner, and Lead Developer are collaborating to define the theme and assign user stories for the next iteration. The team is planning the 7th of 15 iterations in the Release Plan for Release One. The Program Manager displays a Team Velocity chart showing that the Development team has shown significant growth in story points accepted from iterations 1 to 4 and has been leveling off to roughly 200 story points in iterations 5 and 6.
Given there are 9 iterations remaining in the release plan, the Process Owner immediately recognizes there is room for roughly 1800 story points in the remaining time for Release One. However, the backlog contains 2400 story points marked as "high" priority and another 1200 story points marked as "medium" priority. The Process Owner asks to reduce the points assessed to the high priority user stories to bring the total points down to roughly 1800 so as to make them fit in the remaining time. The Program Manager agrees.
What is wrong with this scenario?

正確答案: D
What is the purpose of Performance Data Warehouse?

正確答案: D
A development team is preparing Playback 2. The Playback includes system integrations. When preparing for a playback, what should the program manager do? Advise the development team to:

正確答案: D