最新的SAP Certified Application Associate - Planning and GATP in SAP SCM APO 7.0 EHP1 - C-TSCM44-65免費考試真題

Which statements describe macro capabilities for DP and SNP correctly?
Note: There are 3 correct answers to this question.

正確答案: A,D,E
Which of the PP/DS options can you configure in Model and Version Management?
Note: There are 3 correct answers to this question.

正確答案: B,C,D
Which configuration step(s) allow(s) you to choose a specific variable planning heuristic during interactive planning?

正確答案: C
Your customer creates an infinite multilevel MRP run for a finished product and its components using the process heuristic SAP_MRP_001.
Product heuristics are not maintained in the product masters and no strategy profile is selected in the planning run.
How are the strategy settings derived in this situation?

正確答案: B
Interchangeability master data is maintained in transaction /INCMD/UI.
What do you have to do in order to use the product and/or location interchangeability master data in GATP?
Note: There are 2 correct answers to this question.

正確答案: B,D
Production and capacity planning for several products is finished, resulting in finite scheduled and optimized (setup matrix) planned orders.
How can you transfer the original date, quantity, and capacity situation into the production order?

正確答案: C
An employee uses the detailed scheduling planning board in APO-PP/DS. Although a particular resource is visible on the board, the employee is unable to plan any operations on it.
What is the reason for this?

正確答案: A
Which scenario is supported with the SNP Transport Load Builder?

正確答案: B