When maintaining a work center, formulas can be assigned in the scheduling view. Formulas use formula parameters for calculation. What can be the origin of the formula parameters used for scheduling? (Choose three.)

正確答案: A,C,E
Which of the following efforts can be minimized using the KANBAN procedure?

正確答案: A
In SAP ECC, you calculate the standard available capacity for a work center capacity with the following data: start: 7:00:00 a.m., end. 3:00:00 p.m., break duration: 1 hour, rate of utilization: 80%, overload. 110%, number of individual capacities: 1.
How large is the standard available capacity?

正確答案: D
Which one of the following scheduling types cannot be assigned as default to an order type (production order)?

正確答案: A
In the Customizing for requirements planning, a project team notices that the alternatives P1, P2, P3 and P4 are also delivered as standard in addition to MRP type PD. The number in each of these alternatives represents a firming type. What does a firming type define? (Choose two.)

正確答案: B,C
In the course of a customer project, you are confronted with an SAP ECC system that shows the error message displayed below when you test requirements planning in plant 1000. Large numbers of materials are already available in plant 1000. As a first step in solving the problem, you activate requirements planning in the Customizing for plant 1000.
What further steps must you take before you can put requirements planning in plant 1000 into operation in SAP ECC?

正確答案: D
Which of the following requirements for a manufacturing plant can be supported by using production orders? (Choose three.)

正確答案: A,B,C
A final assembly process takes place at three work centers, one after the other. The routing, which consists of three associated operations (10, 20 and 30), plans for a specific BOM component to be installed during operation 30 and not before. The component should therefore only be requested at the start of operation 30.
What sequence do you follow in master data maintenance in SAP ECC to make this component available in line with operations during final assembly?

正確答案: A