Your organization uses Project Professional 2013 and records actual hours worked on the project.
You manage a small e-commerce website implementation project. One of your testers asks for assistance in completing a critical task, and you find two additional testing resources that can assist with executing the critical test cases.
The total estimated work for the effort-driven task is 100 hours. The original testing resource, Resource1, completes 25 hours of work on the task.
You need to add Resource2 and Resource3 to the task and split the remaining hours across all three resources now working on the task.
Which two actions should you perform? (Each correct answer presents part of the solution.
Choose two.)

正確答案: C,D
You are a project manager who uses Project Professional 2013.
All resources in your project schedule have availability of 8 hours per day. You notice that several of the resources on the project are overallocated. You decide to level the project to help resolve the overallocations for the resources.
Team members often do not work at the same time when completing their work on the tasks.
You need to resolve the overallocations by using the Resource Leveling function.
What should you do?

正確答案: C
You are a project manager who uses Project Professional 2013.
You work in a software development project, which is in progress and has reached 60% of actual progress. Your company decides to use the new Project Reports views to communicate all the project progress across the key users. They also decide to report information about a specific period only, normally one month behind the current day.
You need to access the report view that your company previously created; however, you must only modify the period displayed in the report and ensure that another period will not be presented.
What should you do?

正確答案: A
Your organization uses Project Professional 2013.
A senior stakeholder in a project asks you to determine when a task is over budget by comparing the baseline cost of a task to the cost. Additionally, the senior stakeholder wants you to display a graphic indicator when the baseline cost is greater than the cost.
You write a formula to display the indicator, but it only displays for normal tasks and not for summary tasks.
You need to make the indicator display for summary tasks.
Which two actions should you perform? (Each correct answer presents part of the solution.
Choose two.)

正確答案: A,B
You are a project manager who uses Project Professional 2013.
You are creating a project with several phases. Your customer requires the delivery phase of the project to start on July 1 and to finish within four weeks. The delivery phase includes a summary task, which consists of five separate sub tasks.
You need to monitor this phase closely to ensure that it does not overrun.
What should you do?

正確答案: D
You are managing a project using Project Professional 2013.
Your project schedule is showing task overallocation indicators in the Gantt chart view. You navigate to the Team Planner view to investigate more details regarding the over allocations.
You discover that the BA1 resource is overallocated and you need to see all assignments with details for BA1 to understand their current workload before making any assignment changes.
What should you do?

正確答案: B
You are a project manager, and your organization uses Project Professional 2013.
You have created a detailed project schedule and have identified two tasks that are causing your resource to be overallocated.
You need to use the Team Planner to reassign these tasks from the overallocated resources to underallocated resources with the same skill set.
What should you do?

正確答案: D
You create a new schedule by using Microsoft Project. All calendars and working hours use default settings. You configure the schedule to show all assignment units as decimal values.
A resource reports a reduction in availability for your project by two hours per day.
You need to update the project to reflect the availability of the resource.
What are two possible ways to achieve the goal? Each correct answer presents a complete solution.

正確答案: B,D
說明:(僅 Fast2test 成員可見)
You are a project manager for an organization that uses Project Professional 2013.
You are planning a project schedule that starts on March 1 and lasts four months.
However, the sponsor now asks that the project be delayed to have a finish date of December 31.

正確答案: B,C,E
DRAG DROP
You are using Microsoft PPM.
Your organization provides temporary staff to its customers. Temporary staff members are organized into junior level, standard level, and senior level. Each level is further categorized by two rates. The regular rate is for work within 100 kilometers and a higher rate is for work beyond that distance. You must include all temporary staff and all rates in your schedule.
You need to ensure that Project calculates total resource cost immediately when making a resource assignment. You want the ability to switch between the regular rate and the higher rate for each task.
Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
正確答案:

Explanation:

References: https://support.office.com/en-us/article/Add-resources-to-your-project-
1 a744960-d960-426a-b687-e42ba3f6c0cb
https://support.office.com/en-us/article/Enter-costs-for-resources-b4ced847-2655-4fa4- a621-3fc26fc81c88
https://support.office.com/en-us/article/View-project-cost-totals-0d3a2451-fb1e-4ba0-826e-
20ee3b3d60cc