最新的Oracle Primavera P6 Enterprise Project Portfolio Management 8 Essentials - 1z0-567免費考試真題
Select two true statements regarding calendars.
正確答案: D,F
說明:(僅 Fast2test 成員可見)
In the GANTT Chart. Identify the significance of the blue and green bars.


正確答案: B
說明:(僅 Fast2test 成員可見)
Identity the true statement regarding the Must Finish By constraint.
正確答案: D
說明:(僅 Fast2test 成員可見)
You received an e-mail from a portfolio manager asking you to check performance metrics for the past months on each of the projects filtered for that portfolio.
You cannot locate the portfolio that the email references.
What is the probable cause?
You cannot locate the portfolio that the email references.
What is the probable cause?
正確答案: A
What are two benefits of designating a resource as inactive?
正確答案: C,D
說明:(僅 Fast2test 成員可見)
You are a project manager with a required monthly update cycle. You have marked actual start and actual finish dates for your Physical % complete activities, with % complete calculated from activity steps. You schedule and summarize your project plans. However, your activities are not showing 100% complete. What is the problem?
正確答案: C
Your customer's project teams are cross-functional and global. Therefore, any standard reports must be generated at a standing day/time so that all affected resources and users have clearly defined timelines for data quality checks prior to report creation. Identify the P6 R8 feature that will address this requirement.
正確答案: D
說明:(僅 Fast2test 成員可見)
Identify two formats available in the Capacity Planning chart.
正確答案: C,D
說明:(僅 Fast2test 成員可見)
You are an implementation consultant working at a company where project schedules have been managed primarily with Microsoft Project, on individual desktops. The "projects" theoretically have been multiple-year projects. Your scope of work includes migrating project data from legacy project plans and setting up project planning standards. As you look into the current Microsoft Project plans, it becomes clear that the projects are not really multi-year projects. The plans have been managed by creating "new" projects within the old projects by skipping a few lines in what has become more of a program history.
What approach would you recommend to retain the legacy data (which is a mandated requirement in the new Primavera system), while moving forward with a "one project, one plan" process?
What approach would you recommend to retain the legacy data (which is a mandated requirement in the new Primavera system), while moving forward with a "one project, one plan" process?
正確答案: C