最新的Oracle Project Management Cloud 2024 Implementation Professional - 1z0-1057-24免費考試真題

Your customer has a requirement to import and process third-party transactions that are "costed" and
"accounted".
Which configuration option needs to be set satisfy the requirement? (Choose the best answer.)

正確答案: A
說明:(僅 Fast2test 成員可見)
Identify two correct role templates available on the Oracle Entitlement Server to generate roles for Project Organization Security. (Choose two.)

正確答案: C,D
說明:(僅 Fast2test 成員可見)
Your organization has decided to enable the common accounting and project accounting periods option while defining business unit implementation options.
Where will you maintain the accounting period statuses if this option has been enabled?

正確答案: A
Your customer wants to automatically allocate unassigned asset lines and common costs across multiple assets basedon the construction-in-process cost of each asset.Identify the asset allocation method that you must use as the default method while configuring project types to meet this requirement. (Choose the best answer.)

正確答案: E
說明:(僅 Fast2test 成員可見)
When setting up capitalization options on a project type, you have decided to enable the Require Complete Asset Definition option. If this option is enabled, the "Transfer Assets to Oracle Fusion Assets" process will place asset lines with complete definition into which queue in Oracle Fusion Assets?

正確答案: D
說明:(僅 Fast2test 成員可見)
You have projects and tasks defined with transaction controls, which does not allow certain types of charges to the project. Your business needs to create invoices in AP with this project every period and hence would like to make the process easier by creating a distribution set. As you create the distribution set, you notice that thesedistribution set lines are not validated against the project transaction controlsand you are allowed to save it without any validation errors. Identify thereasonwhy the project transaction controls are notapplied.
(Choose the best answer.)

正確答案: D
說明:(僅 Fast2test 成員可見)
You have a small project for a period of five months. Your budget amount for each month is spread evenly and is $1000 per month. The first month actual expense is $800 and there is a commitment for $600. Now you generate a forecast at the beginning of the second month. Identify the monthly Estimate-To-Complete (ETC) amount that the application would calculate for the remaining four periods, when the ETC generation method includes commitments. (Choose the best answer.)

正確答案: A
說明:(僅 Fast2test 成員可見)
Your customer has separate organizations to maintain indirect, capital, and billing types of projects.
Identify the two setups that can be used to fulfill this requirement. (Choose two.)

正確答案: B,D
說明:(僅 Fast2test 成員可見)
After completing setups in a source environment, your customer wants to move the setup data to a target environment. Identify the two statements related to task list scope, which you must consider before taking a decision based on the customer requirement. (Choose two.)

正確答案: A,B
說明:(僅 Fast2test 成員可見)
Which three tasks can be performed using the project requirements work area? (Choose three.)

正確答案: B,C,D