最新的Oracle Project Management Cloud 2020 Implementation Essentials - 1z0-1057-20免費考試真題

You are trying to create a project purchase order (PO) but you are unable to select Expenditure Organization in the PO. Identify two reasons for this problem. (Choose two.)

正確答案: C,D
說明:(僅 Fast2test 成員可見)
After completing setups in a source environment, your customer wants to move the setup data to a target environment. Identify the two statements related to task list scope, which you must consider before taking a decision based on the customer requirement. (

正確答案: A,D
說明:(僅 Fast2test 成員可見)
Which setup option is common to both financial and project plan types?

正確答案: B
說明:(僅 Fast2test 成員可見)
You are now the project manager of a newly created implementation project. Which two items are not part of managing an implementation project?

正確答案: A,E
Which application generates external roles to grant both function and data security? (Choose the best answer
.)

正確答案: B
說明:(僅 Fast2test 成員可見)
Your customer has different accounting and project accounting periods, and sometimes enters invoices with an invoice date in the open project accounting and closed accounting periods. Which two statements are true about how project accounting and accounting dates will be populated in such invoices? (Choose two.)

正確答案: B,D
Your customer has separate organizations to maintain indirect, capital, and billing types of projects.
Identify the two setups that can be used to fulfill this requirement. (Choose two.)

正確答案: B,D
說明:(僅 Fast2test 成員可見)
Your customer wants to calculate Estimate to Complete (ETC) as the difference between Current Planned Cost and Actual Cost. In Progress Settings, which option would you use in conjunction with the ETC method to meet this requirement? (Choose the best answer.)

正確答案: A
說明:(僅 Fast2test 成員可見)
Your customer started operations and all projects in January 2015. They implemented Enterprise Project Structure for calculating project labor demand by using the Annual option. When they view the labor demand on 15-Dec-2015, the project hierarchy viewer shows data only for the year 2015. The client expected the demand to be shown for a year, from 15-Dec-2015 to 15-Dec-2016.
Identify how the project hierarchy viewer displays labor demand information. (Choose the best answer.)

正確答案: A
說明:(僅 Fast2test 成員可見)
You have four resources in your organization: P, Q, R, and S.
Resource P - Project or resource calendar is active.
Resource Q - Project resource request dates are within the project or resource calendar effective dates.
Resource R - Resource calendar is complex, it does not contain seven days, and it contains more than one pattern and shift.
Resource S - Number of working days within the requested date range is not zero on the project or resource calendar.
Identify the resource for whom Resource Availability Capacity Score will not be calculated. (Choose the best answer.)

正確答案: D
說明:(僅 Fast2test 成員可見)