Select the true statement regarding Global Change.
正確答案: B
As a Sponsoring Company, you want to remove a Partner Company due to its poor performance. When the Partner Company is removed, you also want to ensure that the Partner Company users are inactivated.
What happens if you remove a Partner Company from a Sponsoring Company?
What happens if you remove a Partner Company from a Sponsoring Company?
正確答案: B
You are a program manager for a group of 10+ projects. You actually have a dedicated node for each program, and your owned projects reside under each node. Each program has its own unique requirements for viewing activity dat a. You do not want to ask for activity codes that would be visible to the entire organization. Which activity coding solution would serve the needs of the project managers in your programs?
正確答案: A
Your customer is attempting to implement Resource Capacity Planning using Roles. The Roles Dictionary has been set up by Location, so that Human Resources Is able to determine projected Role shortages Location. The customer's projects are 20 years in duration. What limitation of Resource Capacity Planning may create an issue for the customer?
正確答案: A
View the Exhibit.

Which two statements about the date formula built on the Vendor Active Date field are true?

Which two statements about the date formula built on the Vendor Active Date field are true?
正確答案: A
You are a project manager working with a cross-functional project team. The project spans multiple years and has 25000 activities owned across these cross-functional teams. The team leads for the functional teams do not want to view activities outside of the ones that they own. They have asked you to find a way for them to only see their activities. Identify three P6 EPPM features that would help you respond to this requirement.
正確答案: A,D,E
You are an application administrator. You received a change request to alter the relationship between an EPS node and its associated OBS element. What would be a prudent course of action to complete before moving forward with this change?
正確答案: C
Identify the true statement regarding administrative functions in P6 R8.
正確答案: B
Which two statements are true about Data Definitions?
正確答案: A,B
You are creating a form that includes a mandatory status update Data Element. You want this to be more of a short, conversational field.
Identify the Data Element input type for this use.
Identify the Data Element input type for this use.
正確答案: D
The Total Spending Plan Tally for a project is the sum of the Spending Plans assigned to .
正確答案: C
Select the statement that best describes "Manage Scenarios" functionality.
正確答案: D
Identify the true statement regarding user-interface views.