最新的Oracle Project Management Cloud 2023 Implementation Professional - 1Z0-1057-23免費考試真題
Which product offering simplifies the planning, budgeting, and forecasting capabilities as part of Project Management Cloud?
正確答案: C
說明:(僅 Fast2test 成員可見)
Identify the precedence order in which cost rates are determined for a planning resource when deriving raw costs for rate-based planning resources. (Choose the best answer.)
正確答案: A
說明:(僅 Fast2test 成員可見)
You have four resources in your organization: P, Q, R, and S.
Resource P - Project or resource calendar is active.
Resource Q - Project resource request dates are within the project or resource calendar effective dates.
Resource R - Resource calendar is complex, it does not contain seven days, and it contains more than one pattern and shift.
Resource S - Number of working days within the requested date range is not zero on the project or resource calendar.
Identify the resource for whom Resource Availability Capacity Score will not be calculated. (Choose the best answer.)
Resource P - Project or resource calendar is active.
Resource Q - Project resource request dates are within the project or resource calendar effective dates.
Resource R - Resource calendar is complex, it does not contain seven days, and it contains more than one pattern and shift.
Resource S - Number of working days within the requested date range is not zero on the project or resource calendar.
Identify the resource for whom Resource Availability Capacity Score will not be calculated. (Choose the best answer.)
正確答案: B
說明:(僅 Fast2test 成員可見)
Your customer wants a team member who is assigned to a project to be able to create and submit a forecast, but not to be able to approve the forecast. What is the default project role that you should assign to the person in the project to meet this requirement? (Choose the best answer.)
正確答案: A
說明:(僅 Fast2test 成員可見)
Which three Cost Collection Flexfield core attributes can be derived during import if not explicitly entered in a transaction document? (Choose three.)
正確答案: A
說明:(僅 Fast2test 成員可見)
Your customer wants to assign the Net 45 payment term to all sets except for the corporate business unit specific set, which is assigned the Net 15 payment term. At transaction entry, the list of values for payment terms consists of only one set of data: the set that is assigned to the transaction''s business unit.
Which reference data sharing method would you set up to meet the customer requirement? (Choose the best answer.)
Which reference data sharing method would you set up to meet the customer requirement? (Choose the best answer.)
正確答案: A
說明:(僅 Fast2test 成員可見)
Which three features are part of Oracle Fusion Functional Setup Manager?
正確答案: D
說明:(僅 Fast2test 成員可見)