You are a program manager. You use Project Server 2013 and Project Professional 2013 to manage your portfolio which includes master projects and sub-projects.
There is a mandatory Enterprise Custom Field called Business Unit that provides lookup values so that project managers can categorize their sub-projects. The Business Unit field has been added to all of the Project Center views.
You need to show all projects within Project Center grouped by business unit.
Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
There is a mandatory Enterprise Custom Field called Business Unit that provides lookup values so that project managers can categorize their sub-projects. The Business Unit field has been added to all of the Project Center views.
You need to show all projects within Project Center grouped by business unit.
Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
正確答案: B,C
You are a Project Server 2013 administrator, and you support the Project Management Office (PMO) project managers who need to estimate project hours and costs without knowing the specific resource names.
There are options available to accommodate this request when creating resources on Project Server 2013.
You need to allow project managers to plan workload and cost from the task level up.
What should you do?
There are options available to accommodate this request when creating resources on Project Server 2013.
You need to allow project managers to plan workload and cost from the task level up.
What should you do?
正確答案: C
You are a project manager who uses Project Online. Your project is scheduled to run for at least 18 months. You create a schedule for the first six months, including estimated resource demand, using Project Professional 2013.
For planning purposes, you need to reserve proposed demand for the final 12 months.
What should you do?
For planning purposes, you need to reserve proposed demand for the final 12 months.
What should you do?
正確答案: D
You are a team member for an organization that assigns your tasks on schedules. Single-entry mode is not enabled.
At the end of the week, you submit your timesheet in Project Server 2013. Default security settings are enabled. However, a task assigned to you should have been assigned to a coworker who does the same type of work and who has other tasks on the schedule.
The project manager who assigns the tasks is unavailable.
You need re-assign this task to your co-worker.
What should you do?
At the end of the week, you submit your timesheet in Project Server 2013. Default security settings are enabled. However, a task assigned to you should have been assigned to a coworker who does the same type of work and who has other tasks on the schedule.
The project manager who assigns the tasks is unavailable.
You need re-assign this task to your co-worker.
What should you do?
正確答案: A
You are a project manager who uses Project Server 2013 and Project Professional 2013. You build a project with common tasks for which many resources on your team can be used.
Because your resources have responsibilities outside of the project, you would like to have them assign themselves to tasks they are able to complete.
You need to configure your resources to enable this method of assigning tasks.
What should you do?
Because your resources have responsibilities outside of the project, you would like to have them assign themselves to tasks they are able to complete.
You need to configure your resources to enable this method of assigning tasks.
What should you do?
正確答案: A
You are a project manager who has standard permissions, and your organization uses Project Server 2013.
Some of your resources consistently update their assignments correctly. You want to accept their future updates without review.
You need to begin accepting their updates without review by using the least amount of effort possible.
What should you do?
Some of your resources consistently update their assignments correctly. You want to accept their future updates without review.
You need to begin accepting their updates without review by using the least amount of effort possible.
What should you do?
正確答案: A
You are a project manager for an organization that uses Project Server 2013. When you publish a new schedule, a default Project Site is created for you.
A team member asks you to create a task list separately from the schedule. The team member wants to use the list for specific work they need to perform in order to complete one of the assignments in the project schedule.
On your Project Site, you have the tasks that they have asked for in a task list. The work being performed by this team member becomes critical to the success of your overall schedule.
Management asks for a simple report showing them the task list in an easy-to-read format.
You need to implement this request.
What should you do?
A team member asks you to create a task list separately from the schedule. The team member wants to use the list for specific work they need to perform in order to complete one of the assignments in the project schedule.
On your Project Site, you have the tasks that they have asked for in a task list. The work being performed by this team member becomes critical to the success of your overall schedule.
Management asks for a simple report showing them the task list in an easy-to-read format.
You need to implement this request.
What should you do?
正確答案: C
An organization has performed a portfolio analysis in Project Server 2013 by defining a list of drivers and establishing the prioritization for next year's portfolio.
You are finalizing the second quarter for the next year, which is when changes to the strategy will take place. For transparency reasons, the organization intends to keep historic analysis for a certain number of years.
You need to reevaluate your portfolio for the rest of the year, considering new projects and current executing projects.
Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
You are finalizing the second quarter for the next year, which is when changes to the strategy will take place. For transparency reasons, the organization intends to keep historic analysis for a certain number of years.
You need to reevaluate your portfolio for the rest of the year, considering new projects and current executing projects.
Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
正確答案: A,B
You are a project manager for an organization that uses Project Server 2013.
After performing a review of all the risks created by your project team for one of your projects, you realize that the risks are not linked to their related tasks.
You need to link the risks to their related tasks.
What should you do?
After performing a review of all the risks created by your project team for one of your projects, you realize that the risks are not linked to their related tasks.
You need to link the risks to their related tasks.
What should you do?
正確答案: C
The IT department uses Project Online services to analyze the projects they will execute the next year. Four projects in the pool with their respective priority and costs are shown in the exhibit. (Click the Exhibit button.)

The team wants to get the most value from their portfolio, with the cost constraint indicated.
There are some last-minute restrictions that could change their selection; the CEO indicates that the CRM Global Training project must occur when the CRM Deployment Project takes place.
As the portfolio analyzer, you need to assist the team in achieving their goals.
You force-in the CRM Global Training project. What are two results of this action? (Each correct answer presents part of the solution. Choose two.)

The team wants to get the most value from their portfolio, with the cost constraint indicated.
There are some last-minute restrictions that could change their selection; the CEO indicates that the CRM Global Training project must occur when the CRM Deployment Project takes place.
As the portfolio analyzer, you need to assist the team in achieving their goals.
You force-in the CRM Global Training project. What are two results of this action? (Each correct answer presents part of the solution. Choose two.)
正確答案: C,D