最新的Microsoft TS: Microsoft Project Server 2010, Configuring - 070-177免費考試真題
You have a Project Server 2010 environment. A team leader has accidently approved a proposed project. You need to allow the team leader to reject the proposed project, while making sure the project is listed on the monthly Rejected Proposed Project report. What should you do?
正確答案: A
You are upgrading from Project Server 2007 to Project Server 2010. You need to ensure that only Project Professional 2010 client computers can connect to Project Server 2010. What should you do?
正確答案: B
You have a Project Server 2010 environment. A project is checked out to another user.
You need to delete the checkedout project. Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
You need to delete the checkedout project. Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
正確答案: B,C
You have a Project Server 2010 environment. You need to configure Project Server so that project managers can assign team leads as approvers for tasks in their projects. Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
正確答案: A,C
You have a Project Server 2010 environment. You need to ensure that a new workflow has its own project plan template for all new IT department projects. What should you do?
正確答案: A
You have a Project Server 2010 environment. You create an enterprise project field.
Your need to ensure that project managers fill in the new field for all new projects created in Project Web App (PWA). What should you do?
Your need to ensure that project managers fill in the new field for all new projects created in Project Web App (PWA). What should you do?
正確答案: D
You have a Project Server 2010 environment. A developer creates, tests, and deploys a workflow to the farm. You need to make the workflow available in Project Web App (PWA). Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
正確答案: B,C
You have a Project Server 2010 environment. You create a new enterprise task field. You need to create an aggregated pivot analysis of the new enterprise task field. What should you do?
正確答案: A