最新的BICSI Registered Communications Distribution Designer (RCDD) - RCDDv14免費考試真題
An ICT distribution designer is preparing a price quote for a building design with multiple floors originally sized at 40.000 ft (3716 m2). While the designer is preparing the quote, the structural engineer indicates the building has been increased in size to accommodate an additional 40,000 ft2 (3716 m3) per floor. The designer's recommendation to the engineer will be to increase the slot area by_____for each additional 40,000 ft3 (3716 m2)
正確答案: C
The program manager completed the program's benefits analysis and planning activities. What will this ensure tor the program?
正確答案: A
Which two of the following are means in which radiated interference primarily enters electronic devices?
(Select two options.)
(Select two options.)
正確答案: D,E
Which two of the following documents MUST be submitted by the communication's project contractor for review and approval? {Select two options.)
正確答案: C,D
The program manager must define the program and understand the organization's target market and customer needs. What should the program manager do first?
正確答案: C
A program manager is responsible for constructing a USS50 million building Management suggests it will take three years to complete The program manager can select a design-build option to optimize the construction schedule to 1 5 years However heavy demand for steel is causing price increases and delivery delays. II this trend continues, it could take as long as 4.5 years to complete construction. You learn that a new technology can yield a definitive delivery schedule of 1 25 years What is the expected time of delivery?
正確答案: C
A program is midway through the program delivery phase when a key stakeholder asks if the program is meeting its defined objectives.
How should the program manager demonstrate the program's progress"?
How should the program manager demonstrate the program's progress"?
正確答案: B
A component project manager escalates an issue regarding a key stakeholder to the program manager. The key stakeholder does not respond to emails or phone calls and the project manager believes this key stakeholder is exhibiting a negative attitude toward the work. The key stakeholder has a significant influence over the component project which could impact other components if delays occur. The program manager's attempts to reach the stakeholder via email also fail.
What should the program manager do next?
What should the program manager do next?
正確答案: B
An ICT distribution designer is estimating the installation of five units of 1.5 m (5 ft) tong channel basket trays connected together in the ceiling. The total length of the pathway needed is 7 5 m (25 ft). How many supports will be needed''
正確答案: E
When sizing an underground entrance facility, what is the MINIMUM amount of 103 metric designator conduits (4 trade size) that should be specified by the ICT distribution design?
正確答案: A
An ICT distribution designer is reviewing design documents with the owner to gam approval for an ER design.
Which of the following information about the site shall be included?
Which of the following information about the site shall be included?
正確答案: A
In a design type Scope of Work (SoW) the ICT distribution designer is responsible for providing
正確答案: B
Company A acquires company B.
Which leads to a two-year program lo integrate the processes and systems Company B uses a different project management process, and the company's staff is unhappy about the acquisition As a result company B's project team fails to provide status and cost data in a format that conforms to the program standards.
What should the program manager do first?
Which leads to a two-year program lo integrate the processes and systems Company B uses a different project management process, and the company's staff is unhappy about the acquisition As a result company B's project team fails to provide status and cost data in a format that conforms to the program standards.
What should the program manager do first?
正確答案: D
What is used to facilitate MINOR changes to the Project Requirements?
Request lot Information (RFI)
Request lot Information (RFI)
正確答案: D
A biometrics firm has a facial recognition program with multiple components and project managers The project manager from the mobile device division escalates a vendor-related risk to the program manager After assessing the risk, the program manager determines that this risk may impact other projects within the program. However, this risk has a low degree of Impact and probability of occurring What should the program manager do first?
正確答案: B