An owner requests a cost estimate for a project during the design phase with an estimated present-day budget of $10M. Construction is scheduled for 24 months. Escalation is 5% for the project duration. What is the projected cost for the project?

正確答案: D
說明:(僅 Fast2test 成員可見)
An agency CM is assigned to a new construction project using the CMAA A-2 Standard Form of Agreement between owner and contractor. The project is experiencing concurrent critical path delays caused by the contractor and the architect. What is the BEST guidance the agency CM could give the owner for dealing with these events?

正確答案: B
說明:(僅 Fast2test 成員可見)
A project manager is working on a new transit station project. This client has never used an agency CM before. The project manager wishes to engage the client in defining the scope, budget, schedule, environmental conditions, and basic systems to be utilized. Which of the following would be MOST useful in engaging the client and defining the project requirements?

正確答案: D
說明:(僅 Fast2test 成員可見)
Which schedule process determines the earliest times that schedule activities can start and Finish, and the total project duration?

正確答案: D
說明:(僅 Fast2test 成員可見)
A project in schematic design with sustainability goals will soon begin a value engineering study. Which of the following would ensure that the value engineering study will not harm the project's sustainability?

正確答案: B
說明:(僅 Fast2test 成員可見)
During the design phase of a CM agency project, the designer submits several design options for the stakeholders to review and provide input on. Whose responsibility is it to ensure that the stakeholders are able to provide input on the designs?

正確答案: D
說明:(僅 Fast2test 成員可見)
A dispute arises during construction after the contractor encounters what they feel is unsuitable material. The CM is not notified about the areas of concern, and the contractor hauls 10.000 cy of material offsite. Three months later, the contractor submits a claim for additional cost to haul the material off. The CM should advise the owner that

正確答案: D
說明:(僅 Fast2test 成員可見)