最新的SAP Certified Associate - SAP S/4HANA Cloud Private Edition, Production Planning and Manufacturing - C_P2W22_2504免費考試真題

What does the material type influence?
Note: There are 2 correct answers to this question.

正確答案: A,D
Which operations are considered in the capacity scheduling table?
Note: There are 2 correct answers to this question.

正確答案: B,D
How would you define a pegging structure for an order in the context of Advanced Planning?

正確答案: D
Your company produces a finished good based on a forecast and expects it to be in stock when customers order it. If customers order more than the forecasted quantity, this must NOT have any impact on the production program.
Which planning strategy do you use?

正確答案: C
Which settings can you make in a production scheduling profile?
Note: There are 3 correct answers to this question.

正確答案: A,B,D
Which of the following are possible configuration steps when setting up the alert monitor in Advanced Planning? Note: There are 2 correct answers to this question.

正確答案: A,C
In which master data objects do you maintain data to determine the duration of an operation for production?
Note: There are 2 correct answers to this question.

正確答案: B,C
What are the possible results of a production planning run in Advanced Planning (PP/DS)?
Note: There are 2 correct answers to this question.

正確答案: C,D
Your project team decides to use a make-to-order planning strategy for a strategic material in discrete manufacturing. What are the impacts of this decision?
Note: There are 3 correct answers to this question.

正確答案: A,C,E