最新的ISTQB Certified Tester Advanced Level - Test Manager - CTAL-TM-001免費考試真題

You are writing the project test plan and are analysing the following risks in the project risk register:

Which would be the MOST appropriate test activities to mitigate the product risks?

正確答案: D
說明:(僅 Fast2test 成員可見)
You have assembled the following cost of quality numbers 200 defects were found prior to release and 100 were found after.
Given this information what is the total cost of quality for this project?

正確答案: D
說明:(僅 Fast2test 成員可見)
Your team has been assigned to lest a new product that is tightly integrated with existing systems The integrations include data transfers and transformations You have access to the architectural design documents and the integration specifications and some of your testers are former developers.
Given this information, what is the most appropriate test approach?

正確答案: B
說明:(僅 Fast2test 成員可見)
Assume that you are part of a team conducting test design for a new university system that will allow students to update their own personal information. The Test Strategy states that positive and negative testing should be carried out. along with performance, security and interoperability testing against all new requirements.
The following requirements have been identified by stakeholders:
1. Students must be able to make changes to the following information:
a Name (due to marital status)
b Marital status
c. Home address
d. Home telephone number
e. Email address
f. Mobile telephone number
g. Contact details in case of emergency
2 Only Reception staff must have access to the information held.
3 The system must support 2000 concurrent users and details updated on the system within 20 seconds.
4. Interoperability of the new system with the other systems maintained by the University for student Registrations.
Test analysis for functional and non-functional testing has iust bequn and the following test conditions have been identified:

Which one of the following is a valid test condition that is missing from the table of test conditions and has clear traceability back to the test strategy and requirements?
SELECT ONE OPTION

正確答案: B
You are the Test Manager on a new project. The schedule is aggressive and will require the team to work at peak efficiency. The requirements are not well defined yet, but it is clear that the project will be using new technologies. To help the developers meet the development schedule, an offshore group will be added to the development team.
At this time there is not enough budget to add more testing resources. The project stakeholders are very concerned about the quality of the delivered product and will be watching the project closely, particularly during the testing cycles. The exit criteria from the system test level require no open high priority/severity defects, 100% pass rate for all test cases covering risks that are classified as "high" or "very high", 95% pass rate for all "medium" risks and 75% pass rate for all "low" and "very low" risks.
Given this information, which of the activities of the standard test process are the most critical for the Test Manager to perform? [3]

正確答案: B
說明:(僅 Fast2test 成員可見)
You are preparing the estimate for the test plan, which should cover all test activities subsequent to the plan having been agreed. Estimation of test activities has in the past been embarrassingly inaccurate. Historical data from previous similar projects is unreliable, but for two recent projects it is possible to find out how many test cases were developed and how long this took.
Which TWO of the following estimation techniques will be BEST in this scenario?

正確答案: B,D
說明:(僅 Fast2test 成員可見)
Which testing metric identifies defect density?

正確答案: B
說明:(僅 Fast2test 成員可見)
Refer to SCENARIO 1
Week 4 of test execution has been completed and the following test report has been produced

Review this report against the organisational Test Strategy, what is the status of the Test Strategy objectives?
SELECT ONE OPTION

正確答案: C
You feel that your team has become lazy when applying good software testing techniques You have given each of them a challenge to take a different business rule and build a full decision tableand then collapse that table You will then assess the results For this assessment, what competencies are you validating?

正確答案: D
說明:(僅 Fast2test 成員可見)
As the Test Manager working for a company developing safety related software for defence equipment, you have been asked to consider how you can track test progress and report on the following:
1) Test cases adequately cover all requirements
2) Issues relating to safety critical vulnerabilities are being addressed in priority order
3) How much of the developed system has been exercised through testing What tools would help to achieve this?
SELECT ONE OPTION

正確答案: D
You have written a defect report and have just been notified that it is in the "returned" state.
Who should take action on this defect? [1]

正確答案: C
說明:(僅 Fast2test 成員可見)