While opening an organization tree on the Manage Organization Trees page, you notice that the hierarchy status is displayed as Inactive. Identify the two reasons for the organization tree to be in Inactive status. (Choose two.)

正確答案: A,C
說明:(僅 Fast2test 成員可見)
Which three can be tracked as Status tracking for Project Invoice Approval Notifications? (Choose three.)

正確答案: A,B,C
說明:(僅 Fast2test 成員可見)
You are set up as a Follower in Manage Tasks. Which two abilities can you accomplish? (Choose two.)

正確答案: A,C
說明:(僅 Fast2test 成員可見)
You are implementing Project Portfolio Management (PPM) for a professional services firm. The firm rents multiple buildings for its operations. At the end of each month, they review the rent expense for the month and want to allocate the rental cost to all the projects and tasks that are executed by associates in each of the buildings. The source amounts must be proportionally allocated to the tasks based on the raw costs of the tasks from the previous month. Considering that all these costs are in General Ledger, what three allocation setups should you complete in PPM? (Choose three.)

正確答案: B,D,E
說明:(僅 Fast2test 成員可見)
Your customer wants a team member who is assigned to a project to be able to create and submit a forecast, but not to be able to approve the forecast. What is the default project role that you should assign to the person in the project to meet this requirement? (Choose the best answer.)

正確答案: B
說明:(僅 Fast2test 成員可見)
Your customer started operations and all projects in January 2015. They implemented Enterprise Project Structure for calculating project labor demand by using the Annual option. When they view the labor demand on 15-Dec-2015, the project hierarchy viewer shows data only for the year 2015. The client expected the demand to be shown for a year, from 15-Dec-2015 to 15-Dec-2016.
Identify how the project hierarchy viewer displays labor demand information. (Choose the best answer.)

正確答案: A
說明:(僅 Fast2test 成員可見)
A project administrator is trying to assign a team member for a project but cannot find the person in the team member list on the Project Definition page. What is the reason for this problem? (Choose the best answer.)

正確答案: D
說明:(僅 Fast2test 成員可見)
You have a small project for a period of five months. Your budget amount for each month is spread evenly and is $1000 per month. The first month actual expense is $800 and there is a commitment for $600. Now you generate a forecast at the beginning of the second month. Identify the monthly Estimate-To-Complete (ETC) amount that the application would calculate for the remaining four periods, when the ETC generation method includes commitments. (Choose the best answer.)

正確答案: A
說明:(僅 Fast2test 成員可見)
You are currently involved in the implementation of the Project Financial Management solution for your client organization. Your client organization has two main lines of business: Consulting and Support. Consulting Services and Support Services organizations have different project planning, management, analysis and reporting requirements for the projects that they manage, though the management reporting and transaction processing requirements are the same for both the organizations.
What will be your recommendation?

正確答案: C
說明:(僅 Fast2test 成員可見)